Hackney cable works
Find out what cable installation works are planned or underway near you in Hackney - and read the notification letter for each one.
Find works near you
The blue line on the map below represents the full route in Hackney, which will be completed in phases. Navigate by using the map, or enter your postcode into the search bar to see where activity is planned relative to your property or business or has taken place near you.
Latest news
Below you can find the latest resident and business notifications for planned cable installation works in Hackney. The three updates shown here reflect the newest or future works notifications. You can also expand the list below to view all Hackney works notifications.
Hoxton Street Phase 4.1 cable installation revisit
View notificationNew North Road – Phases 22 and 23
View notificationFanshaw Street – Phases 7 and 8
View notificationUse the dropdown below to view all other Hackney works notifications in chronological order, with the most recent works shown first.
View all Hackney works notifications22
- Underway
Hoxton Street – Phase 6
Hoxton Street, between Fanshaw Street and McGreggor Court
From 3 August 2026 for approximately 3 weeks
- Underway
New North Road – Phase 19.1
New North Road, between the junctions with Minton Street and Rushton Street
From 30 July 2026 for approximately 2 weeks
- Completed
New North Road Phase 19.2 cable installation works
New North Road, Wimbourne Street to Rushton Street
From 17 June 2026 for approx. 2 weeks
- Completed
Old Street Phase 2 cable installation works
Old Street, Kingsland Road to Hoxton Street
From 15 June 2026 for approx. 3 weeks
- Completed
Old Street Phase 3.2 weekend excavation works
Old Street, Kingsland Road and Hackney Road, between 15 Hackney Road and Courthouse Hotel Shoreditch
Saturday 13 and Sunday 14 June 2026
- Completed
New North Road Phases 17.1 and 17.2 cable installation works
New North Road, Cherbury Street to Salvation Army Hoxton Community Church
From 22 May 2026 for approx. 5 weeks
- Completed
Hoxton Street Phase 6 cable installation works
Hoxton Street, Fanshaw Street to 40 Hoxton Street
From 19 May 2026 for approx. 3 weeks
- Completed
Pitfield Street Phase 12 weekend cable installation works
Pitfield Street, Fanshaw Street to New North Road
Saturday 9 and Sunday 10 May 2026
- Completed
Hoxton Street Phases 4.1 and 4.2 cable installation works
Old Street, Hoxton Square and Hoxton Street, between Courthouse Hotel Shoreditch and the junction of Hoxton Street with Mundy Street
From 14 April 2026 for approx. 5 weeks
- Completed
New North Road Phases 16.1 and 16.2 cable installation works
New North Road, 29 New North Road to Salvation Army Hoxton Community Church
From 9 April 2026 for approx. 7 weeks
- Completed
New North Road Phase 13 weekend cable installation works
New North Road, Pitfield Street to 41 New North Road
Saturday 4 and Sunday 5 April 2026
- Completed
Old Street Phases 3.1 and 3.2 weekend excavation works
Old Street, Kingsland Road and Hackney Road, between 15 Hackney Road and Courthouse Hotel Shoreditch
Weekends from 28 March to 26 April 2026
- Completed
New North Road Phase 13 weekend cable installation works
New North Road, Pitfield Street to 41 New North Road
Saturday 28 and Sunday 29 March 2026
- Completed
Hoxton Street Phase 5 cable installation works
Hoxton Street, Jobcentre Plus to 40 Hoxton Street
From 27 March 2026 for approx. 3 weeks
- Completed
Hackney Road Phase 1 weekend excavation works
Hackney Road at the junction of Austin Street
Saturday 21 and Sunday 22 March 2026
- Completed
New North Road Phase 20 weekend excavation works
New North Road, Wimborne House to Eagle Wharf Road Bus Shelter, Stop XL
Weekends from 21 March to 5 April 2026
- Completed
Hackney Road Phase 1 cable installation works
Hackney Road at the junction of Austin Street
From 18 March 2026 for approx. 1 week
- Completed
New North Road Phase 13 cable installation works
New North Road, Pitfield Street to 41 New North Road
From 18 March 2026 for approx. 3 weeks
- Completed
Pitfield Street Phase 11 weekend cable installation works
Pitfield Street, Fanshaw Street to New North Road
Saturday 14 and Sunday 15 March 2026
- Completed
New North Road / Mintern Street weekend cable installation works
New North Road, Mintern Street to Nevitt House
Weekends from 21 February to 15 March 2026
- Completed
Pitfield Street weekend cable installation works
Pitfield Street, Fanshaw Street to New North Road
Weekends from 24 January to 15 February 2026
- Completed
Fanshaw Street cable installation works
Fanshaw Street, Hoxton Street to Pitfield Street
From 19 January 2026 for approx. 8 weeks
Project timeline
- 19 January 2026Start on site
- January to May 2026Fanshaw Street and Pitfield Street initial works
- March to June 2026Hackney Road, Hoxton Street and New North Road main phase works
- June to early July 2026Old Street Phase 2 and New North Road Phase 19.2We are here
- July to August 2026New North Road continuing phases and Fanshaw Street revisit works
- September to early October 2026New North Road Phase 22 / Phase 23 and Hoxton Street Phase 4.1 revisit works
- October to November 2026New North Road and Hoxton Street final revisit works
- 10 November 2026Programme completion
Please note this programme is indicative and subject to change. For the latest detailed information, please refer to the works notifications above.
Questions or concerns?
If these works affect you and you need more information, please get in touch.