Islington cable works
Find out what cable installation works are planned or underway near you in Islington – and read the notification letter for each one.
Find works near you
The blue line on the map below represents the full route in Islington, which will be completed in phases. Navigate by using the map, or enter your postcode into the search bar to see where activity is planned relative to your property or business or has taken place near you.
Latest news
Below you can find the latest resident and business notifications for planned cable installation works in Islington. The updates shown here reflect the newest or most relevant works notifications. You can also expand the list below to view all Islington works notifications.
Arundel Square – Phase 47
View notificationLough Road – Phases 57 and 58
View notificationLough Road – Phases 66 and 67
View notificationUse the dropdown below to view all Islington works notifications in reverse chronological order, with the newest start date first.
View all Islington works notifications9
- Underway
Arundel Square – Phase 47
Arundel Square, from outside no. 1 to the junction with Ellington Street
From 10 August 2026 for approximately 2 weeks
- Underway
Lough Road – Phases 57 and 58
Lough Road, from outside New River College Secondary to the junction with Sheringham Road
From 5 August 2026 for approximately 3 weeks. Phase 58 runs from 5 to 18 August, followed by Phase 57 from 18 to 28 August.
- Underway
Lough Road – Phases 66 and 67
Lough Road, from the substation near Piper Close to the junction with George’s Road
From 5 August 2026 for approximately 5 weeks. Phase 67 runs from 5 to 25 August, followed by Phase 66 from 25 August to 10 September.
- Underway
Arundel Place – Phase 42
Arundel Place, from outside no. 5 to near the junction with Offord Road
From 29 July 2026 for approximately 1 week
- Completed
Ellington Street Phases 49 and 50 cable installation works
Ellington Street, between Arundel Place and no. 50 Ellington Street
From 3 June 2026 for approx. 3 weeks
- Completed
Laycock Street Phases 32, 33, 36 and 37 cable installation works
Laycock Street, between Laycock Primary School and the junction with Liverpool Road
From 23 May 2026 for approx. 5 weeks, in phases along the road
- Completed
Arundel Place Phase 42 cable installation works
Arundel Place, between Offord Road and Blackthorn Avenue
From 14 May 2026 for approx. 2 weeks
- Completed
Arundel Place Phase 46 cable installation works
Arundel Place, between Ellington Street and Arundel Square
From 23 April 2026 for approx. 3 weeks
- Completed
Westbourne Road Phase 55 cable installation works
Westbourne Road, between Sheringham Road and no. 22 Westbourne Road
From 23 April 2026 for approx. 3 weeks
Project timeline
- 23 April 2026Westbourne Road Phase 55 and Arundel Place Phase 46 works begin
- April to May 2026Westbourne Road and Arundel Place Phase 46 works continue
- 14 May 2026Arundel Place Phase 42 works begin
- 23 May to late June 2026Laycock Street Phases 32, 33, 36 and 37 works take place in phases along the roadWe are here
- 3 June to late June 2026Ellington Street Phases 49 and 50 works take place, including temporary traffic lights for the first week of works
- Late June 2026Current notified Islington works sequence expected to complete, subject to permits, construction sequencing and conditions encountered beneath the highway
Please note this programme is indicative and subject to change. For the latest detailed information, please refer to the works notifications above.
Questions or concerns?
If these works affect you and you need more information, please get in touch.