This page provides information about planned cable installation works and related construction activity in Hackney. Our planned activity covers a number of locations in the borough, including Fanshaw Street, Pitfield Street, Hackney Road, Hoxton Street and New North Road.
Route overview
This map shows the full length of our proposed works in Hackney, which will be completed in segments. To use the map, please enter your postcode into the search bar to see what activity is planned or has taken place near you. You can also click on individual route segments or markers to view the relevant works notification.
Project timeline
- 19 January 2026Start on site
- January to May 2026Fanshaw Street and Pitfield Street initial works
- March to June 2026Hackney Road, Hoxton Street and New North Road main phase works
- June to early July 2026Old Street Phase 2 and New North Road Phase 19.2
- July to August 2026New North Road continuing phases and Fanshaw Street revisit works
- September to early October 2026New North Road Phase 22 / Phase 23 and Hoxton Street Phase 4.1 revisit works
- October to November 2026New North Road and Hoxton Street final revisit works
- 10 November 2026Programme completion
Please note this programme is indicative and subject to change. For the latest detailed information, please refer to the works notifications below.
Latest news
Below you can find the latest resident and business notifications for planned cable installation works in Hackney. The three updates shown here reflect the newest or future works notifications. You can also expand the list below to view all Hackney works notifications.
Hoxton Street Phase 4.1 cable installation revisit
View notificationNew North Road Phase 19.2 cable installation works
View notificationOld Street Phase 2 cable installation works
View notificationUse the dropdown below to view all other Hackney works notifications in chronological order, with the most recent works shown first.
View all Hackney works notifications18
Old Street Phase 3.2 weekend excavation worksSaturday 13 and Sunday 14 June 2026
Location: Old Street, Kingsland Road and Hackney Road, between 15 Hackney Road and Courthouse Hotel Shoreditch
Works date(s): Saturday 13 and Sunday 14 June 2026
View notificationNew North Road Phases 17.1 and 17.2 cable installation worksFrom 22 May 2026 for approx. 5 weeks
Location: New North Road, Cherbury Street to Salvation Army Hoxton Community Church
Works date(s): From 22 May 2026 for approx. 5 weeks
View notificationHoxton Street Phase 6 cable installation worksFrom 19 May 2026 for approx. 3 weeks
Location: Hoxton Street, Fanshaw Street to 40 Hoxton Street
Works date(s): From 19 May 2026 for approx. 3 weeks
View notificationPitfield Street Phase 12 weekend cable installation worksSaturday 9 and Sunday 10 May 2026
Location: Pitfield Street, Fanshaw Street to New North Road
Works date(s): Saturday 9 and Sunday 10 May 2026
View notificationHoxton Street Phases 4.1 and 4.2 cable installation worksFrom 14 April 2026 for approx. 5 weeks
Location: Old Street, Hoxton Square and Hoxton Street, between Courthouse Hotel Shoreditch and the junction of Hoxton Street with Mundy Street
Works date(s): From 14 April 2026 for approx. 5 weeks
View notificationNew North Road Phases 16.1 and 16.2 cable installation worksFrom 9 April 2026 for approx. 7 weeks
Location: New North Road, 29 New North Road to Salvation Army Hoxton Community Church
Works date(s): From 9 April 2026 for approx. 7 weeks
View notificationNew North Road Phase 13 weekend cable installation worksSaturday 4 and Sunday 5 April 2026
Location: New North Road, Pitfield Street to 41 New North Road
Works date(s): Saturday 4 and Sunday 5 April 2026
View notificationOld Street Phases 3.1 and 3.2 weekend excavation worksWeekends from 28 March to 26 April 2026
Location: Old Street, Kingsland Road and Hackney Road, between 15 Hackney Road and Courthouse Hotel Shoreditch
Works date(s): Weekends from 28 March to 26 April 2026
View notificationNew North Road Phase 13 weekend cable installation worksSaturday 28 and Sunday 29 March 2026
Location: New North Road, Pitfield Street to 41 New North Road
Works date(s): Saturday 28 and Sunday 29 March 2026
View notificationHoxton Street Phase 5 cable installation worksFrom 27 March 2026 for approx. 3 weeks
Location: Hoxton Street, Jobcentre Plus to 40 Hoxton Street
Works date(s): From 27 March 2026 for approx. 3 weeks
View notificationHackney Road Phase 1 weekend excavation worksSaturday 21 and Sunday 22 March 2026
Location: Hackney Road at the junction of Austin Street
Works date(s): Saturday 21 and Sunday 22 March 2026
View notificationNew North Road Phase 20 weekend excavation worksWeekends from 21 March to 5 April 2026
Location: New North Road, Wimborne House to Eagle Wharf Road Bus Shelter, Stop XL
Works date(s): Weekends from 21 March to 5 April 2026
View notificationHackney Road Phase 1 cable installation worksFrom 18 March 2026 for approx. 1 week
Location: Hackney Road at the junction of Austin Street
Works date(s): From 18 March 2026 for approx. 1 week
View notificationNew North Road Phase 13 cable installation worksFrom 18 March 2026 for approx. 3 weeks
Location: New North Road, Pitfield Street to 41 New North Road
Works date(s): From 18 March 2026 for approx. 3 weeks
View notificationPitfield Street Phase 11 weekend cable installation worksSaturday 14 and Sunday 15 March 2026
Location: Pitfield Street, Fanshaw Street to New North Road
Works date(s): Saturday 14 and Sunday 15 March 2026
View notificationNew North Road / Mintern Street weekend cable installation worksWeekends from 21 February to 15 March 2026
Location: New North Road, Mintern Street to Nevitt House
Works date(s): Weekends from 21 February to 15 March 2026
View notificationPitfield Street weekend cable installation worksWeekends from 24 January to 15 February 2026
Location: Pitfield Street, Fanshaw Street to New North Road
Works date(s): Weekends from 24 January to 15 February 2026
View notificationFanshaw Street cable installation worksFrom 19 January 2026 for approx. 8 weeks
Location: Fanshaw Street, Hoxton Street to Pitfield Street
Works date(s): From 19 January 2026 for approx. 8 weeks
View notification